AVISO
Parada Temporal del Servicio de la Pasarela.
Los días 13, 14, 15, 20, 21 y 22 de noviembre el acceso a la pasarela permanecerá cerrado de 10:00 de la mañana a 16:00 de la tarde.


It’s suspended by 70 steel cables called hangers. In fact, the structure is not welded or riveted to the towers or pillars, but only supported by these hangers, which bear a significant portion of the weight, and supported by the corbels, a kind of capitals attached to the towers that help to evenly distribute the weight of the deck. Hence the nickname “hanging”, as the crossbeam truly hangs from the towers, although many associate it with the suspension of the gondola.
In its origins, a cable and pulley traction system was used, powered by a steam boiler located in one of the two towers of the Bridge. The current gondola is the fifth in the history of the Bridge. Vehicle and passenger transportation takes place inside it, hanging from a 36-wheel, 25-meter-long carriage that moves along the tracks of the upper horizontal beam. The control station is located on the ground floor of one of the towers in Portugalete, for better visibility.
The current travel duration between the two banks of the river is one minute and a half.
The gondola has a capacity for 6 vehicles (passenger cars) and 200 passengers (100 in each cabin), and can be supplemented with 6 motorcycles or bicycles.
Two panoramic elevators have been installed to access the walkways for tourist visits, one on each side of the Bridge, accessible through the terraces.
The Puente Bizkaia was the first transporter bridge built in the world, but its technological uniqueness does not only lie in the development and operation of a transfer mechanism (gondola, carriage, and rail), but also in its spectacular iron structure and the use of steel cables to secure that structure.
INNOVATION IN THE BRIDGE

The existing gondola was substituted for another more in line with the technological progress.
Innovative boarding halls were constructed with automatic systems.
The payment systems were unified, eliminating the personal ticket offices and installing self-payment systems.
The entire installation is automated via the control room.
Preparation of the draft project for a suspension bridge with a mobile vehicle adapted to large estuaries, in secret conversations between Alberto Palacio and Ferdinand Arnodin.
November 5.
Simultaneous presentation of the invention patent application by Alberto Palacio, in Bilbao, and Ferdinand Arnodin, in París.
February 20.
Presentation of the Vizcaya Bridge construction project.
February 12.
Concession of the licence to build the bridge between Portugalete and Getxo, after overcoming the technical reluctance of the engineers from the Ministry for Promotion’s Public Works Department.
April 7.
Constitution of the company “Martín Alberto Palacio y Compañía” with the aim of constructing and operating the Bridge.
Construction of the Vizcaya Bridge, with Alberto Palacio as works director, Ferninand Arnodin as constructor and with the technical assistance of the engineer A. Brull.
The pillars are made of profiles forged in Le Creusot. The replaceable cables are of mild steel from the Firminy wireworks. The wiring by the workshops of Ferdinand Arnodin in Chateauneuf-sur-Loire. The deck is made up of a beam with Saint Andrew crosses made of mild steel by the Altos Hornos de Vizcaya blast furnace rolling mill, Assembled at the Zorroza workshops in Bilbao. The suspension of the beam is mixed, using vertical suspension cables and inclined shrouds. The energy supplied by a two cylinder vertical steam boiler with water pump, produced by Henri David in Orleans, moves the cables which pull the gondola. The motor system is placed in a large hut placed between the two towers on the Getxo side.
The original conception by Alberto Palacio to obtain the movement was a cart moved by compressed air (Mekarsky system).
The company is concerned about the complication of a steam boiler situated high up and the services for its operation.
An electric motor is installed to replace the boiler in the same place. The lift which was not able to be installed before due to the lack of electric supply is installed in Tower 2. The stairs are passed to Tower 1.
June 16.
Members of the Military Engineers Corps made controlled explosions of the parabolic bases of the Vizcaya Bridge on the Getxo side to make it temporarily useless for the enemy forces, and not to destroy it completely.
Reconstruction of the Vizcaya Bridge, with the project by the engineer José Juan Aracil, works management by Luis Alberto Ribed and construction by the company Sociedad Ibérica de Montajes. The parabolic cables, the deck, the suspension system, the cart, the gondola and the anchoring block on the Getxo side were all replaced. The only two significant modifications from its original design related to the beam and the suspension system.
The mixed suspension by suspension cables and shrouds characterised the empirist period of the first generation of suspension bridges, in which the function of the shrouds was analogical to that of the braces of the beam bridges. But the coexistence between both elements created uncertainty which made it impossible to make the calculation and adjustment between both suspension systems. The frequent breakages and the difficulties in the maintenance led to their almost generalised replacement, and occurred in the construction of the Brooklyn Bridge in 1935, or in the construction of the Rouen shuttle bridge.
However the elimination of the shrouds in the Vizcaya Bridge reduced its rigidity and therefore forced an increase in the beam’s inertia, which went from having an edge of two metres in the original project to three metres in the reconstruction. The primitive Saint Andrew crosses method was also changed for a Warren bean which had the advantage of being more reduced secondary efforts.
The new beam, the cart and the gondola were made by the company Compañía Anónima Basconia, the cables by the company Sociedad Franco Española de Cables, the suspension cables and the reconstruction of the top of the towers on the Getxo side were done by the company Sociedad Ibérica de Montajes and the new anchoring blocks in the Getxo side by Erdaide and Barrenechea.
The previous machine house was taken down and the new one, slightly smaller, was placed in a large hut higher up at the end of the deck at Getxo. The replacement of the electrical motor, which had been installed in 1901, was done by the company Eguren.
Initially the movement was controlled from a lookout point situated in the middle of the gondola.
June 19.
Inauguration of the restored Vizcaya Bridge.
Elimination of the driving cabin in the gondola and the introduction of a cabin on the pillars on the Getxo side on the deck, attached to the machines hut next to Tower 2.
April 14.
Substitution of the gondola for a new unit built with aeronautical criteria and technique in Props and using materials resistant to marine corrosion.
March15.
Installation of a lighting system for night time performances with over 900 lighting points.
December.
Preparation by the future operating company of a General Report on the State of the Bridge’s Structures and Mechanisms.
A non-postponable programme is prepared to remove auxiliary elements which are at risk of collapsing, making urgent reinforcements and repairs and to create auxiliary elements necessary to proceed to the following general repairs:
The following work was carried out:
The following work was carried out:
The following work was carried out:
A new light lighting system is installed.
Load resting criteria were corrected and trials were performed with anti-friction wheels.
Some broken cords were repaired and the Creditrans application was introduced .
Parada Temporal del Servicio de la Pasarela.
Los días 13, 14, 15, 20, 21 y 22 de noviembre el acceso a la pasarela permanecerá cerrado de 10:00 de la mañana a 16:00 de la tarde.